Published 18 November 2026 · 16 min read
- The installation process, step by step: A well-run solar installation follows the same order almost every time, and knowing it helps you spot a shortcut.
- What a proper quote should list: A good quote is specific enough that you could give it to a second installer and ask for a comparison.
- What solar installation costs: As of late 2026, prices vary by brand and site, so use these ranges as a starting point for budgeting, not as a quotation.
- Who may legally install solar in South Africa: Solar installations are electrical work, and in South Africa electrical installation work is regulated.
- Municipal versus Eskom-supplied areas: Who supplies your electricity decides who you register with.
The installation process, step by step
A well-run solar installation follows the same order almost every time, and knowing it helps you spot a shortcut.
- Site survey: the installer inspects the roof, the distribution board, the supply size and the cable routes, and asks for recent electricity bills.
- Design: panels, inverter, battery, protection devices and cable sizes are chosen to suit your usage, roof and budget.
- Quote: a written, itemised proposal with model numbers and a clear scope.
- Approvals: estate, body corporate or HOA consent where needed, and any municipal application that must be lodged before you connect.
- Installation: usually one to three days for a home, longer for larger or commercial systems. Mounting goes first, then panels, DC cabling, inverter and battery, AC connection and labelling.
- Testing and commissioning: insulation, earth and polarity tests, followed by the system being switched on and checked against the design.
- Certificate of Compliance (CoC): issued by a registered person for the electrical work.
- SSEG registration: the system is registered with your municipality or Eskom if it is grid-connected.
- Handover: you receive documents, warranty information, monitoring access and a walk-through of how the system behaves.
If an installer skips the survey, the CoC or the registration, treat that as a warning sign rather than a time saver.
What a proper quote should list
A good quote is specific enough that you could give it to a second installer and ask for a comparison. At the least it should name the following.
- Panels: brand, model, wattage and quantity, with the product and performance warranty periods.
- Inverter: brand, model, kVA or kW rating, whether it is hybrid or grid-tied, and warranty.
- Battery: brand, model, usable capacity in kWh, chemistry, cycle life and warranty.
- Mounting system: rail type and material, and how it suits your roof.
- Electrical items: DC and AC isolators, breakers, surge protection, cabling, earthing and a new or modified distribution board.
- Labour: what is included, such as roof penetration sealing and commissioning.
- Compliance: the CoC, municipal registration and who submits it.
- Monitoring: the app or portal, and who sets it up.
- Payment terms: deposit, milestone payments and balance, plus the estimated timeline.
- Exclusions: anything not covered, such as DB upgrades, trenching or structural work.
Be cautious about quotes that say only "5 kW solar system" with no brands. That wording lets a seller swap in cheaper parts later. Also check the VAT treatment and whether the installer's company details and physical address are on the document.
What solar installation costs
As of late 2026, prices vary by brand and site, so use these ranges as a starting point for budgeting, not as a quotation. They assume installed systems with VAT, mounting, labour and a CoC, in or near a metro.
- Small grid-tied system, about 3 kW with no battery: roughly R30,000 to R55,000.
- Home hybrid backup system, about 5 kW inverter with 5 kWh battery: roughly R70,000 to R120,000.
- Mid-size home hybrid, about 8 kW inverter with 10 kWh battery: roughly R120,000 to R200,000.
- Large home or small business, 10 to 12 kW with 15 to 20 kWh storage: roughly R200,000 to R350,000.
- Commercial grid-tied arrays without batteries: often roughly R10 to R17 per watt, falling with size.
What moves the price: battery size and brand, inverter quality, roof type and access, distance from the distribution board, whether the DB needs upgrading, and how many panels the roof can take. A cheaper quote is not always a better deal, and a more expensive one is not always better engineering. Compare scope, brands and warranties side by side, then decide.
Who may legally install solar in South Africa
Solar installations are electrical work, and in South Africa electrical installation work is regulated. A person who installs, alters or connects a fixed electrical installation must be a registered person under the Electrical Installation Regulations, and a Certificate of Compliance must be issued on completion. A registered electrician or a registered installation electrician with the right scope should sign that CoC for the work.
PV GreenCard is a voluntary quality programme run in the industry that trains and registers installers and carries out inspections of their work. It is not a legal licence, but many insurers, estates and buyers like to see it, and it is a helpful way to separate trained installers from casual ones. Ask to see current registration details and check them with the issuing body.
A professional engineer may also be needed on larger or commercial projects, especially where structural loading or protection design is involved. If an installer cannot name the registered person who will sign off your CoC, or says a certificate is not necessary, do not proceed. A system without a CoC can complicate insurance claims, sales of your property and connection to the grid.
Municipal versus Eskom-supplied areas
Who supplies your electricity decides who you register with. If your property is supplied directly by Eskom, you deal with Eskom. If you are in a municipal area, which includes most metros and many towns, you register with the municipality, which buys power from Eskom and resells it to you.
For grid-connected systems the process usually involves a small-scale embedded generation (SSEG) application, which asks for system details, the CoC, equipment certificates and sometimes single-line diagrams and inverter data. Some municipalities charge application or inspection fees, require approved inverters, or have rules about export, metering and tariff changes. Systems without any grid connection, such as fully off-grid homes, usually face fewer administrative steps, though electrical compliance still applies.
The key points are the same everywhere. Do not connect an inverter to the grid without approval. Do not assume your neighbour's experience is yours, because rules differ between municipalities and change from time to time. Ask your installer which authority applies to your address, who will submit the application, and what the current fees and timelines are. A professional installer deals with these steps weekly and should be able to explain them clearly.
Registration differences across the metros
The big metros all expect grid-tied systems to be registered, but the details differ and keep changing, so check current rules before you commit.
- City of Johannesburg and City Power: SSEG registration is required, with documentation and equipment requirements set by the utility, and typically an inspection or approval step.
- City of Tshwane: an application process with technical and compliance documents, and rules on export and metering.
- City of Ekurhuleni: a registration process with its own forms, and requirements that can differ between supply areas.
- City of Cape Town: a well-known SSEG application route, with specific rules on approved inverters, feed-in and tariffs.
- eThekwini (Durban): an application route with its own requirements on metering and approvals.
- Nelson Mandela Bay: an application process that can involve inspection and specific technical conditions.
- Mangaung (Bloemfontein): a registration requirement, with documents and conditions set by the municipality.
Describing these in general terms is deliberate. Tariffs, feed-in arrangements, fees and forms are updated often. Before you sign, ask the installer to confirm the current requirements for your area, or contact the municipal electricity department directly and ask for the current SSEG process in writing.
Roof types and mounting
Mounting is where many installation problems start, so the roof type deserves attention before the panels do.
- IBR and corrugated metal sheeting: panels are fixed with clamps or rails to the purlins or ribs, using sealed fasteners. Fixing only into thin sheeting without finding the structure is a common error.
- Concrete tile: stainless or galvanised hooks are fixed to the rafters, slipped under tiles, and the tiles are cut or shaped where needed. This should be done without cracking tiles.
- Slate, Harvey tile and decorative roofs: need more care and sometimes a roof specialist, because tiles are fragile and costly to replace.
- Flat concrete roofs: tilted frames held down by ballast or anchors. Waterproofing must not be damaged, so check if penetrations are allowed.
- Ground mounts and carports: concrete footings or driven piles, with attention to wind and soil conditions.
Wind loads, rust, galvanic corrosion between dissimilar metals and waterproofing at penetrations all matter. Ask what the rails are made from, how penetrations are sealed and whether the roof has the strength for the extra weight. A mismatch between roof, rail and clamp is a leak waiting to happen.
DC and AC protection, earthing and surge protection
Protection devices are the unglamorous part of a solar job and the part that keeps your house safe.
On the DC side, between panels and inverter, a proper installation includes correctly rated DC isolators, appropriately sized solar cable (UV-rated and double insulated), good quality MC4-compatible connectors crimped with the right tool, and DC surge protection. Strings must be arranged so voltage stays within the inverter's input window, including on cold winter mornings when voltage rises.
On the AC side, expect a dedicated breaker for the inverter output, residual current protection where required, an isolator, correct cable sizing and labelling, and changes to the distribution board that keep backup and non-backup circuits separate and safe.
Earthing connects metal frames, rails and the inverter to the earth system so a fault has a safe path. Surge protection reduces damage from lightning-induced surges, which is a real concern on the Highveld. In high-lightning areas, ask about lightning protection and surge arrestors on both the DC and AC sides. Good labelling, tidy cable routing and photographs of the finished work are signs of a careful installer.
Estates, HOAs and sectional title approvals
Many South African homes sit in estates, complexes or sectional title schemes, and solar often needs permission before work begins.
In an estate with a homeowners association, check the architectural guidelines. Some estates limit panel visibility from the street, set rules on roof tilt or colour, and require plan approval. In sectional title schemes, the roof is usually common property, so a body corporate or trustees must usually approve any installation, and may need a formal resolution, an agreement on roof use and rules about who pays for what.
Start the conversation early, because committee meetings can take weeks. Provide the committee with a clear proposal that includes panel layout, mounting method, structural and waterproofing details, insurance cover and the installer's credentials. For complexes, discuss shared options such as a communal system. Get the approval in writing and keep it with your documents.
If approval is refused, ask for the reason. Sometimes a change in layout, a different panel colour or an agreement about maintenance responsibility resolves the objection without losing the project.
Insurance and bond implications
Solar equipment is expensive, and it changes what you must tell your insurer and, in some cases, your bank.
Inform your home insurer before or soon after the installation. Ask whether panels, inverter and battery are covered as part of the building or as contents, whether hail, lightning, theft and fire are included, and whether there are conditions such as requiring a CoC or a registered installer. Some insurers ask for an updated sum insured. Battery fire risk is a topic some insurers raise, so ask for placement guidelines, and install batteries in a ventilated, protected location, not stacked against a wall in a closet.
If you have a home loan, the property value may increase after installation, but check your bond agreement before making structural changes. Some lenders offer home improvement or green finance. If the system is financed through a third party, read who owns the equipment and what happens if you sell.
A complete handover pack, including the CoC, system diagram, equipment serial numbers and registration confirmation, makes insurance claims and property sales much smoother.
City by city: Johannesburg, Pretoria, Cape Town, Durban, Gqeberha
Every city brings its own practical wrinkle.
Johannesburg: Summer thunderstorms and lightning are the main hazard, so insist on proper surge protection and earthing. Check the current City Power registration process before you connect.
Pretoria: Plenty of older houses with concrete tile roofs and older distribution boards. Ask for a check of the DB and wiring before adding an inverter, because an old board may need upgrading.
Cape Town: Wind and salt air are the issues, particularly along the coast. Choose corrosion-resistant mounting hardware and stainless fasteners, and size for the cloudy, rainy winter if you want battery independence.
Durban: Heat, humidity and salt shorten the life of cheap fittings and electronics. Specify inverters and enclosures with good ingress protection and place them out of direct sun and spray.
Gqeberha: Strong wind is the dominant concern, so ask for the wind-load design on the mounting system and make sure clamps and rails are properly rated.
City by city: Bloemfontein, Polokwane, Mbombela, Rustenburg, Kimberley
Bloemfontein: Hot summers and cold winters with big temperature swings. Protect battery rooms from both extremes, and confirm Mangaung's registration route before you start.
Polokwane: Very high heat, so choose panels with a good temperature coefficient, leave space behind the array for airflow, and keep inverters in shade.
Mbombela: Humid, with heavy summer storms and dust in some areas. Check lightning protection, waterproofing at roof penetrations and ventilation for equipment.
Rustenburg: Mining and industrial dust coats panels quickly, so plan on regular cleaning and consider how you will reach the roof safely. Mining-area power can be uneven, so good surge protection matters.
Kimberley: Strong sun and extreme heat with dusty conditions. Panels and inverters must cope with sustained high temperatures, and a clear cleaning plan will protect your output. Distances to service teams can be long, so ask who will actually come out if something fails.
Installing for SADC customers
SA Solar Hub works with customers in Botswana, Namibia, Zimbabwe, Zambia and Mozambique as well as across South Africa. Installation outside South Africa works differently, because South African regulations do not apply across the border.
There are generally two routes. In the first, we supply the equipment, with documentation and technical guidance, and a local electrician or installer in your country carries out the work and signs it off under local rules. In the second, we plan the design, supply a full kit with labelled strings and diagrams and, for suitable projects, discuss on-site supervision or commissioning support.
Practical points matter. Check what your national utility or regulator requires for grid-connected systems, and which local electrical standards apply. Confirm import duties, taxes and any permits with your own revenue authority or a clearing agent before you pay for equipment, because they differ per country and change over time. Plan for spare parts, since delays at borders can be costly, and consider whether remote monitoring is possible given the local internet connection. For off-grid sites, size the system for the weakest season and think carefully about who will maintain it.
How long does installation take?
Timelines depend on stock, approvals and site complexity more than on the physical work.
- Survey and quote: a few days to a week from first contact.
- Approvals from an estate or body corporate: one to several weeks, sometimes longer.
- Equipment availability: usually days if stock is local, longer for specific brands or large battery orders.
- Physical installation: one to three days for most homes, three to ten days for larger systems and commercial sites.
- CoC and handover: often on completion or within a few days.
- Municipal registration: variable, from a couple of weeks to a few months depending on the authority and its workload.
A realistic total, from signing to a fully registered system, is often two to six weeks for a standard home, and longer where approvals drag or equipment is back-ordered. Be wary of anyone promising a system "tomorrow" with no survey, and equally wary of an installer who takes your deposit then goes quiet for months. Ask for a written schedule with the main milestones and agree what happens if dates slip.
Red flags when choosing an installer
Most installation disasters can be seen coming. Watch for these signs.
- No physical address, no company registration details and no verifiable past work.
- Reluctance to show registration credentials or name the person who will sign the CoC.
- A quote with no brands or models, or one that says "or equivalent".
- Pressure to pay a large upfront deposit, or payment into a personal account.
- A price far below every other quote, which usually means cheaper parts or skipped steps.
- Promises that a system will cut your bill to zero, or will run everything including a stove, geyser and aircon on a small battery.
- No site visit, or a survey that never looks at your distribution board.
- Vague answers about registration with the municipality.
- No written warranty, or a warranty that depends on you chasing overseas manufacturers.
Ask for references you can contact, and ask to see completed jobs. Read online reviews with some care, since some are not independent. A good installer will welcome the questions and answer them without defensiveness.
Aftercare, monitoring and warranties
The handover is the start of the relationship, not the end. At handover you should receive the CoC, the system diagram, equipment details and serial numbers, warranty documents and registration confirmation, along with a walk-through of how the system works in different situations such as load shedding, cloudy days and a full battery.
Monitoring is worth having. Most modern inverters have an app or portal showing production, consumption, battery state and faults. Make sure it is set up on your Wi-Fi and in your name, and ask who can see it. Good monitoring lets you spot a failed string or a tripped breaker quickly.
Understand the warranty layers. Panels, inverter and battery each have a manufacturer warranty, and the installer gives a separate workmanship guarantee that covers installation faults such as leaks and loose connections. Ask how claims work, who handles shipping and replacement, and whether loan units are available for inverters.
Book a check after the first few months, then yearly. Look at connections, clamps, labels, surge devices and battery settings. A system that is looked after will keep performing well.
DIY limits and the legal position
Many people ask whether they can install solar themselves. The honest answer is that you may do some things, but not everything.
Buying and handling panels is not restricted. However, fixed electrical installation work must be done by or under the supervision of a registered person, and a Certificate of Compliance must be issued. Connecting an inverter to your distribution board or the grid is the clearest example of work that needs registration and sign-off. Doing it yourself without a CoC can invalidate insurance, create liability if something goes wrong, cause problems when you sell the property, and put people at risk of electric shock or fire. DC voltage on a string of panels can be high and dangerous, and panels produce voltage whenever there is light.
A sensible middle route is to hire a registered electrician for the electrical work and the CoC, and not to cut corners on roof safety. Small portable kits and plug-in power stations that are not connected to your installation are a different case, but they still need to be used safely. When in doubt, ask a registered electrician before you start.
Your next step
Start by gathering the basics: six to twelve months of electricity bills, a photo of your distribution board, the roof type and direction, and a note on what you want solar to do for you, whether that is reducing bills, covering load shedding or both.
SA Solar Hub installs solar systems in Gauteng, and we work with customers across all nine provinces and into SADC countries through supply and project support. We start with a survey, design the system around your usage and roof, give you an itemised quote with brands and warranties, and arrange the CoC and registration as part of the job.
If you are comparing quotes from other installers, send them to us and we will explain the differences in plain language. We would rather you make an informed decision than a rushed one. Ask us about timelines, approvals and aftercare, and we will tell you what to expect for your address. Contact us to book a site survey or request a quote.
Frequently asked questions
How much does solar installation cost in South Africa?
As of late 2026, a small grid-tied system of about 3 kW costs roughly R30,000 to R55,000, and a typical 5 kW hybrid with 5 kWh battery roughly R70,000 to R120,000. Prices vary by brand and site, so get an itemised quote that names the brands, warranties and what is included.
Do I need a Certificate of Compliance for solar?
Yes. Solar is a fixed electrical installation, and a registered person must issue a Certificate of Compliance when the work is complete. Without it, you may face insurance problems, difficulty selling your property and trouble registering a grid-connected system with your municipality or Eskom.
Do I have to register my solar system with the municipality?
If your system is connected to the grid, you generally must register it as small-scale embedded generation with your municipality or Eskom. Rules, fees and forms differ by area and change over time, so ask your installer to confirm the current process for your address.
What is PV GreenCard?
PV GreenCard is a voluntary quality programme for solar installers in South Africa, which trains and registers installers and inspects completed work. It is not a legal licence, but it is a useful sign of competence. You still need a registered person to sign the Certificate of Compliance.
How long does it take to install solar panels?
The physical installation usually takes one to three days for a home. From signing to full registration, a standard home often takes two to six weeks, longer if an estate or body corporate approval is needed or if equipment is back-ordered. Municipal registration timelines vary by authority.
Can I install solar panels myself?
You can buy panels, but the electrical connection must be done by or under a registered person, and a Certificate of Compliance must be issued. Doing it yourself can void insurance, cause legal problems and create real safety risks, especially from high DC voltage and wiring faults.
Do I need approval from my HOA or body corporate?
Often yes. Estates may have architectural rules, and in sectional title schemes the roof is usually common property, so trustees or the body corporate must approve the installation. Start early, submit a clear proposal and keep the approval in writing.
Will solar affect my home insurance?
Yes, so tell your insurer. Ask whether panels, inverter and battery are covered, including hail, lightning and theft, and whether they require a Certificate of Compliance or a registered installer. Keep the handover documents and serial numbers safe for any future claim.
How do I choose a good solar installer near me?
Choose an installer with a verifiable address and company details, a registered person who signs the Certificate of Compliance, a site visit and an itemised quote naming brands and warranties. Ask for references and completed jobs, and be wary of very low prices or big upfront deposits.
Does SA Solar Hub install outside Gauteng and South Africa?
We install in Gauteng and serve all nine provinces through supply and project support. For SADC countries such as Botswana, Namibia, Zimbabwe, Zambia and Mozambique we supply equipment and technical guidance, and confirm local duties and electrical requirements with your own authorities and a local installer.
Solar panels and installation by province
By city
SADC countries we supply
Shop by category
Official sources
- Department of Employment and Labour (Electrical Installation Regulations, CoC)