Published 25 November 2026 · 8 min read
- Why the Ekurhuleni application matters: If your home or business in Germiston, Boksburg, Benoni, Kempton Park, Alberton, Springs, Brakpan, Edenvale or Tembisa is supplied with electricity by the City of Ekurhuleni, a solar system that can feed power back into the grid needs the municipality's approval.
- First, confirm who actually supplies your electricity: Ekurhuleni is a large metro and not every address is supplied by the municipality.
- What the application usually contains: The exact checklist depends on the current form, but most municipal SSEG applications ask for a similar set of documents.
- Approval before installation, registration after: There are normally two stages.
- Fees you may come across: Municipalities can charge for processing applications, for inspections, for meter changes and for connecting a new bi-directional meter.
Local page: solar installers and prices in Ekurhuleni (East Rand).
Why the Ekurhuleni application matters
If your home or business in Germiston, Boksburg, Benoni, Kempton Park, Alberton, Springs, Brakpan, Edenvale or Tembisa is supplied with electricity by the City of Ekurhuleni, a solar system that can feed power back into the grid needs the municipality's approval. This is called SSEG registration: small-scale embedded generation. It applies to grid-tied and hybrid systems, including hybrid systems that are set to export nothing.
Many owners treat the application as a formality that the installer will sort out later. That is where trouble starts. A system that is switched on without approval can lead to a disconnection notice, a fine, trouble with an insurer, or a problem when you sell the property. The application is not hard, but it is picky, and most delays come from missing paperwork rather than from the municipality being unreasonable.
This guide describes the process in general terms so you know what to expect. Municipal forms, fees, portals and contact points change from time to time, so always download the current forms from the City of Ekurhuleni and confirm the details with the energy or electricity department before you submit anything.
First, confirm who actually supplies your electricity
Ekurhuleni is a large metro and not every address is supplied by the municipality. Some areas, farms, smallholdings and a few industrial pockets are supplied directly by Eskom, and those customers register with Eskom instead. Look at your electricity account. If the account comes from the City of Ekurhuleni, the municipality is your supply authority. If it comes from Eskom, follow the Eskom process.
If you are unsure, ask your installer to check, or call the municipal customer centre with your account or meter number. Doing this first saves you from filling in the wrong set of forms.
What the application usually contains
The exact checklist depends on the current form, but most municipal SSEG applications ask for a similar set of documents. Expect to prepare:
- The completed application form, signed by the account holder or the property owner
- Proof of ownership or the owner's written consent if you rent, plus body corporate or homeowners' association approval where relevant
- A copy of your latest municipal account and your ID or company registration documents
- A single line diagram that shows the panels, inverter, protection, isolators, meter and the point of connection
- Datasheets for the inverter and panels, with proof that the inverter complies with NRS 097-2-1
- The system size in kVA or kW for the inverter and in kWp for the panels
- Details of any battery storage and the configuration (export allowed or zero export)
- The installer's details and, once the work is finished, a valid Certificate of Compliance
A tidy, complete pack is the single best way to avoid a back-and-forth. Keep both digital and printed copies, and note the date you submitted and any reference number you are given.
Approval before installation, registration after
There are normally two stages. The first is the application for approval, which is submitted before the system goes live. The second is the commissioning and registration step, where you show that the installation was done properly and meets the conditions of approval.
Some people install first and apply later because the equipment is already on the roof. It is better not to. Approval can come with conditions, such as a limit on the installed inverter capacity, a requirement to install a specific type of meter or settings that stop export. If those conditions are discovered after the system is built, you may have to rework it.
Ask your installer to submit the application before they order equipment, and to tell you what the municipality said in writing. You want a clear approval, not a verbal assurance.
Fees you may come across
Municipalities can charge for processing applications, for inspections, for meter changes and for connecting a new bi-directional meter. The amounts differ between municipalities, between customer categories and from year to year, and they are set in the municipal tariff schedule. For that reason this article does not quote figures. Look at the current approved tariff book on the City of Ekurhuleni website, or ask the department for a written breakdown.
Some practical points about money:
- Ask whether the application fee is refundable if the application is rejected
- Ask who pays for meter replacement and whether a deposit is involved
- Ask whether there is an annual fixed charge or a change in your tariff category once you register
- Ask whether a feed-in credit exists for exported energy, and how it is paid. Do not assume one exists
If the answers are not in writing, treat them as unconfirmed. This matters most for businesses that are building a business case around exports.
The inverter has to be on the right list
The most common technical reason for a bounced application is the inverter. Municipalities need to know that the inverter meets the grid-connection standard, NRS 097-2-1, and many keep or follow an approved list of inverters. If your inverter is not on that list, or if the datasheet does not show the required certificates, the application will stall.
This is a good reason to speak to your installer before buying equipment, not after. Popular hybrid brands are usually listed, but listing can depend on the exact model and firmware, and lists are updated. Ask the installer to show you the current approval for the model they plan to supply, and to confirm that the grid code settings for South Africa are loaded.
For a hybrid system with batteries, also ask how the export limit will be set. If you want zero export, the application should say so, and the inverter should be configured to match. A mismatch between what you applied for and how the system is actually set up is a classic cause of trouble at inspection.
Common reasons for rejection or delay
Applications are usually sent back for ordinary reasons. These are the ones that come up most often:
- Missing or unsigned owner consent, especially for tenants and sectional title units
- An unclear or incorrect single line diagram, for example one that does not show the protection devices
- An inverter that is not on the approved list or lacks the right compliance documents
- Panel and inverter capacity that does not match what is written on the form
- No Certificate of Compliance, or a certificate issued by someone who is not a registered person
- Outdated forms, because the municipality has issued a newer version
- Illegible scans, or documents that do not match each other (different names, different addresses, different account numbers)
- Work started or finished before approval was given
Most of these are avoidable by checking the pack against the current form line by line before submitting. If an application is rejected, ask for the reasons in writing and fix the specific items rather than starting a fresh application with new errors.
The role of the Certificate of Compliance
A Certificate of Compliance (CoC) is issued by a registered electrician after the installation has been inspected and tested against SANS 10142-1, the wiring code. For a solar installation it confirms that the electrical work on your side of the meter is safe. It is a legal requirement for any electrical installation work, and the municipality will normally ask for it before it registers the system or finalises the connection.
Make sure the person who signs it is registered with the Department of Employment and Labour in the right category, and keep a copy for your insurer. If you wire the system yourself or use an unregistered person, you will not obtain a valid CoC, which will block your registration.
Realistic timelines and how to follow up
Processing times depend on the volume of applications and the staff available, so no honest installer can promise a fixed date. Plan for the approval to take weeks rather than days, and do not schedule the installation date around an assumed approval date.
A few habits help:
- Submit a complete application the first time
- Record the date, reference number and the name of the person you dealt with
- Follow up politely at regular intervals, in writing
- Ask the installer to remain involved until the system is registered, not only until it is switched on
- Keep the approval letter and the final registration confirmation in a safe place
If you have waited a long time without any feedback, escalate within the department before you consider other options. Do not energise a grid-tied system without approval simply because the process is slow.
How this fits with your wider solar plan
The SSEG application is one part of a solar project. You still need to size the system, decide between grid-tied, hybrid and off-grid, and work out whether the savings justify the cost. Registration protects you legally and keeps the municipality informed, but it does not change the physics of your own consumption.
For business owners, there may also be tax implications, such as the Section 12B allowance for renewable energy assets. That is a tax matter, so confirm the details with your accountant or SARS.
If you are comparing quotes, include registration in the comparison. Ask each installer whether they prepare and submit the SSEG application, whether it is included in the price, and what happens if the municipality asks for changes. Quotes that are silent on this point often leave the paperwork with you.
Next step
Before you sign a quote, confirm that your property is supplied by the City of Ekurhuleni, download the current SSEG forms, and ask your installer to walk you through the documents they will submit. SA Solar Hub can assist with sizing, a single line diagram and the application pack for Ekurhuleni customers. Send us your account details and a recent bill, and we will tell you what the process looks like for your property.
Frequently asked questions
Do I need SSEG registration in Ekurhuleni if my hybrid inverter never exports?
Yes, you should still register. Municipalities generally treat any system with an inverter connected to the grid as an embedded generator, even when it is set to zero export. Registration also protects you with your insurer. Confirm the exact requirement with the City of Ekurhuleni and the current form, because rules and wording can change.
How much does an Ekurhuleni SSEG application cost?
Fees are set in the municipal tariff schedule and can change, so check the current tariff book or ask the department for a written quote. Costs may include an application or inspection fee and possibly a meter change. Always ask what is refundable, who pays for the meter and whether your tariff category changes after registration.
Can I submit the application myself without an installer?
You can submit it as the account holder, but you still need technical documents, such as a single line diagram, inverter datasheets and a Certificate of Compliance from a registered electrician. Most owners find it easier when the installer prepares the pack. Either way, you remain responsible for having an approved installation.
What happens if my application is rejected?
Ask the municipality for the reasons in writing, then correct those specific items and resubmit. Common causes are missing owner consent, an unlisted inverter, an unclear diagram or a missing Certificate of Compliance. Do not switch the system on while it is unapproved, because that can lead to penalties or disconnection.
Does a prepaid meter change the process?
Possibly. Prepaid meters often cannot handle reverse flow, so the municipality may require a different meter or a different arrangement. Ask early what is required for your meter type and who carries the cost. The answer can affect both your budget and your timeline.
Is the Eskom process the same as the Ekurhuleni process?
The principles are similar, but the forms, portals and contacts differ. Check your electricity account to see who supplies you. If it is Eskom, use their SSEG process. If it is the City of Ekurhuleni, use the municipal forms and confirm details with the department.
Official sources
- City of Ekurhuleni
- Eskom
- SALGA / AMEU embedded generation resource portal (SSEG)
- SABS (publisher of NRS 097-2-1)
- Department of Employment and Labour (Electrical Installation Regulations, CoC)